Rancangan Sequence Penambangan Batubara Tipe 3A Pit 81W Tambang Batubara PT Antareja Mahada Makmur Jobsite PIK

Authors

  • Faizal Akbar Fachrezy Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung
  • Dudi Nasrudin Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung
  • Linda Pulungan Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung

DOI:

https://doi.org/10.29313/bcsme.v6i2.24358

Keywords:

Kata kunci, maksimal, 3 kata

Abstract

Abtract. This research aims to design an optimized short-term mine sequence to fulfill the specific production target of type 3A coal for the September 2025 period at Pit 81W, PT Antareja Mahada Makmur (AMM), Perkasa Inakakerta Jobsite. The main problem lies in the uncertainty of the tonnage distribution of type 3A coal, which requires high-precision scheduling. The research methodology integrates geological modeling using software and software-based scheduling on seams S74, S79, S79U1, S80, and S81. The optimization results indicate that the total production of type 3A coal reached 202,629 tons, exceeding the company's initial target of 121,338 tons. The volume of overburden removed was 1,469,974 BCM with an optimized stripping ratio (SR) of 7.00, lower than the initial target of 7.51. This success is based on the application of Standard Operational Parameters (SPO) with a Machine Availability (MA) of 90%, Physical Availability (PA) of 90%, Utilization of Availability (UA) of 66.5%, and average Effective Working Hours (EWH) of 14.35 hours. The use of software significantly improved the accuracy of synchronization between mine advancement and the allocation of mechanical units.

Abstrak.

Penelitian ini bertujuan untuk merancang urutan penambangan (mine sequence) jangka pendek yang dioptimalkan untuk pemenuhan target produksi batubara spesifik tipe 3A pada periode September 2025 di Pit 81W, PT Antareja Mahada Makmur (AMM), Jobsite Perkasa Inakakerta. Permasalahan utama terletak pada ketidakpastian distribusi tonase batubara tipe 3A yang memerlukan penjadwalan presisi tinggi. Metodologi penelitian mengintegrasikan pemodelan geologi menggunakan perangkat lunak dan penjadwalan berbasis perangkat lunak per pada seam S74, S79, S79U1, S80, dan S81. Hasil optimasi menunjukkan total produksi batubara tipe 3A mencapai 202.629 ton, melampaui target awal perusahaan sebesar 121.338 ton. Volume overburden yang dipindahkan sebesar 1.469.974 BCM dengan stripping ratio (SR) hasil optimasi sebesar 7,00, lebih rendah dibandingkan target awal 7,51. Keberhasilan ini didasarkan pada penerapan Standar Parameter Operasional (SPO) dengan nilai Machine Availability (MA) 90%, Physical Availability (PA) 90%, Utilization of Availability (UA) 66,5%, dan rata-rata Effective Working Hours (EWH) 14,35 jam. Penggunaan perangkat lunak secara signifikan meningkatkan akurasi sinkronisasi antara kemajuan tambang dengan alokasi unit mekanis.

References

Arif, Irwandny. (2022). Kriteria Rancangan Sequence Penambangan. Jurusan Teknik Pertambangan ITB.
Badan Pusat Statistik. (2023). Data Curah Hujan (2015-2023) dan Keadaan Penduduk Kecamatan Bengalon.
Caterpillar Inc. (2023). Performance Handbook, Edition 45 (Catatan: Anda bisa menuliskan judul lengkap "Caterpillar Performance Handbook, Edition 45: Cycle Time CAT 395 & 777. Caterpillar Inc.
Howard L Hartman, & Jan M Mutmansky. (2002). Intoductory Mining Engineering (Second Edition). The University Of Alabama.
Hustrulid, W. A., Kuchta, M., & Martin, R. K. (2013a). Open Pit Mine Planning and Design, Two Volume Set & CD-ROM Pack. In Jurusan Teknik Pertambangan ITB (Number Kriteria Rancangan Sequence Penambangan). CRC Press. https://www.taylorfrancis.com/books/9781482221176
Hustrulid, W. A., Kuchta, M., & Martin, R. K. (2013b). Open Pit Mine Planning and Design, Two Volume Set & CD-ROM Pack. CRC Press. https://doi.org/10.1201/b15068
Indonesianto, Y. ,. (2013). Pemindahan Tanah Mekanis. Jurusan Teknik Pertambangan,.
Kementerian Energi dan Sumber Daya Mineral. (2025). Pedoman Mine Planning Batubara Tipe 3A Kaltim.
Keputusan Menteri Energi Dan Sumber Daya Mineral Republik Indonesia Nomor 1827 K/30/MEM/2018 Tentang Pedoman Pelaksanaan Kaidah Teknik Pertambangan Yang Baik (2018).
Komatsu Seisakujo. (1990). Komatsu Specification And Application Handbook (12th ed.). Komatsu.
Prodjosumarto, Partanto. (1996). Pemindahan Tanah Mekanis. Institut Teknologi Bandung.
Santoso, B. (2015). Petrologi Batu Bara Sumatra dan Kalimantan: Jenis, Peringkat, dan Aplikasi. LIPI Press.
Santoso, B. (2023). Classification of Coals by Rank. ASTM International. https://doi.org/10.1520/D0388-23
Suwandhi, A. (2004). Perencanaan Jalan Tambang. Diktat Perencanaan Tambang Terbuka. Jurusan Teknik Pertambangan UNISBA.
Taylor, H. K. (2020). Pit Geometry and SR Optimization for GAR 4800 Coal: SME Handbook. Society for Mining, Metallurgy & Exploration.