Perencanaan Alat Gali Muat dan Alat Angkut untuk Mencapai Target Produksi Pengupasan Overburden pada Penambangan Batubara PT XYZ di Kecamatan Loa Janan, Kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur.

  • Arrafi Zaqi Ramadhona Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung
  • Zaenal Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung
  • Noor Fauzi Isniarno Teknik Pertambangan, Fakultas Teknik, Universitas Islam Bandung
Keywords: Match Factor, Kebutuhan Alat Gali Muat, Kebutuhan Alat Gali Angkut, Produktivitas

Abstract

Abstract. PT XYZ is a coal mining company located in Batuah Village and Tani Harapan Village, Loa Janan District, Kutai Kertanegara Regency, East Kalimantan Province. Currently, the company is preparing a Feasibility Study for development. In carrying out its mining activities, it uses an Open Mining System with the Strip Mine type. The purpose of this study is to determine the type of equipment, the number of needs from the number of its fleet in meeting the total overburden stripping production target, which is 76,000,000 BCM OB for 10 years.This company has two pits, namely the South Pit and the North Pit. This research activity was only carried out at the North Pit which focused on planning the needs of loading and hauling equipment. Based on the results of the study, the number of excavators needed to achieve the overburden stripping production target from the first to the tenth year is 5 units. While the number of transport equipment needed to achieve the overburden stripping production target is the first year 31 units. The types of excavators used are the SANY SY1250H Excavator and the SANY SKT160S Dump Truck.

Abstrak. PT XYZ merupakan perusahaan tambang batubara yang berada di Desa Batuah dan Desa Tani Harapan, Kecamatan Loa Janan, Kabupaten Kutai Kertanegara, Provinsi Kalimantan Timur. Pada saat ini perusahaan sedang menyusun Studi Kelayakan penambangan. Dalam melakukan kegiatan penambangannya menggunakan Sistem Tambang Terbuka dengan tipe Strip Mine. Tujuan dari penelitian ini adalah untuk mengetahui jenis alat, jumlah kebutuhan dari jumlah armadanya dalam memenuhi target produksi total pengupasan overburden, yaitu 76.000.000 BCM OB selama 10 tahun. Pada perusahaan ini mempunya dua pit, yaitu Pit Selatan dan Pit Utara. Kegiatan penelitian ini hanya dilakukan pada Pit Utara yang berfokus pada perencanaan kebutuhan alat gali muat dan alat angkut. Semua perhitungan menggunakan rumus-rumus teori Pemindahan Tanah Mekanis. Berdasarkan hasil penelitian, didapatkan jumlah alat gali muat yang diperlukan  untuk  mencapai target produksi pengupasan overburden  dari tahun pertama sampai tahun kesepuluh adalah 5 unit.  Sedangkan jumlah alat angkut yang  diperlukan  untuk  mencapai target produksi pengupasan overburden  adalah tahun pertama 31 unit. Adapun jenis alat gali muat yang digunakan adalah  Excavator SANY SY1250H dan  alat angkut Dump Truck SANY SKT160S.

References

Rizky Noor Fitriadi, Iswandaru, & Elfida Moralista. (2024). Pengaruh Geometri Jalan Terhadap Produktivitas Alat Angkut. Jurnal Riset Teknik Pertambangan, 41–48. https://doi.org/10.29313/jrtp.v4i1.3821

Sa Putra, A., L. D. J Usup, H., & Noveriady. (2023). Analisis Kemajuan Tambang Terhadap Perancangan Mine Plan pada Aktivitas Overburden Removal. Jurnal Riset Teknik Pertambangan, 157–166. https://doi.org/10.29313/jrtp.v3i2.3077

Waode Jelita Ma’ruff Bay, & Linda Pulungan. (2022). Pemanfaatan Bahan Galian Mineral Kalsit Berdasarkan Karakteristik Sifat Fisik di Cikembar Sukabumi. Jurnal Riset Teknik Pertambangan, 40–47. https://doi.org/10.29313/jrtp.v2i1.994

Andi Tenrisukki Tenriajeng, 1987, “Pemindahan Tanah Mekanis”. Penerbit Gunadarma.

Anonim, 2018, “Kepmen ESDM No. 1827 Tahun 2018 Tentang Pedoman Pelaksanaan Kaidah Teknik Pertambangan Yang Baik”.

Anonim 1993. “AASHTO guide for Design of Pavement Structures”. America. American

Association of State Highway and Transportation Officials.

Bangun, Filianti Teta Ateta, 2009, “Pengembangan Tanah Mekanik dan Alat Berat”, Departemen Teknik Sipil, Universitas Sumatera Utara, Sumatera Utara.

Badan Pusat Statistik (BPS) Kabupaten Bungo, 2020, “Kabupaten Bungo Dalam Angka 2023”, Katalog BPS: 1102001.1509.

Hasanah, Dilla, dkk., 2021, “Penentuan Nilai Keserasian (Match Factor) Untuk Optimalisasi Alat Berat Pada Pekerjaan Pemindahan Tanah Penutup Pertambangan Batubara PT Tri Bakti Sarimas”, JuPerSaTek, Volume 4, Nomor 1, Juni 2021, 480-491.

Indonesianto, Yanto, 2006, “Pemindahan Tanah Mekanis”, Jurusan Teknik Pertambangan UPN Veteran Yogyakarta”, Yogyakarta.

Indonesianto, Yanto, 2008, “Pemindahan Tanah Mekanis”, Yogyakarta: UPN “Veteran” Yogyakarta.

Kaufman, W.W., dan Ault, J.C., 2001, “Design of Surface Mine Haulage Roads – A Manual”, Pittsburch: WMC Resoources Ltd.

Lambung, Tommy Youthberth, 2016, “Evaluasi Jalan Tambang Untuk Meningkatkan Produktivitas Alat Angkut Pada Aktivitas Pemindahan Overburden”, Jurnal GEOSAPTA, Volume 2, Nomor 2, Juni 2016, 108-112.

Pranama, dkk., 2015, “Evaluasi Jalan Angkut Dari Front Tambang Andesit Ke Crusher II Pada Penambangan Batu Andesit Di PT Gunung Kecapi, Kabupaten Purwakarta, Provinsi Jawa Barat”. Jurnal Teknologi Pertambangan, 1 (2): 61-68.

Pratomo, Kurniawan Nur, dkk., 2016, “Kajian Teknis Produksi Alat Gali-Muat dan Alat Angkut Untuk Memenuhi Target Produksi Pengupasan Overburden Penambangan Batubara PT CitraTobindo Sukses Perkasa Kabupaten Sarolangun Provinsi Jambi”. Prosiding Tekniki Pertambangan, Volume 2, Nomor 2, Agustus 2016.

Prodjosumarto, Partanto, 1993, “Pemindahan Tanah Mekanis”,Bandung: Institut Teknologi Bandung.

Rochmanhadi, 1992, “Alat-Alat Berat dan Penggunaannya”, Jakarta: Yayasan Badan Penerbit Pekerjaan Umum.

Rosidi, H.M.D., Tjokrosapoetro, S., Pendowo, B., Gafoer, S., dan Suharso, 1996, “Peta Geologi Lembar Painan dan Bagian Timur Laut Lembar Muarasiberut, Sumatera”, Pusat Penelitian dan Pengembangan Geologi.

Silvia, Sukirman, 1999, “Dasar-Dasar Perencanaan Geometrik Jalan”, Bandung: Nova.

Published